Saturday, January 26, 2013

Construction Contracts Bill

There has been a lot of talk emanating from the CIF, the Irish Concrete Federation and also some TD's and Senators in relation to the new construction contracts bill. This talk is along the lines that if this bill was currently in place then some recent problems on sites would not occur.

Random statements are coming into the public domain without any real substance or backup to justify why this pending piece of legislation would somehow magically save sub-contractors.

The latest on this is to do with the Brian McCarthy Ltd Pepsi site in Cork where sub-contractors are owed money and are threatening to blockade the site.

Any new legislation that will improve matters is certainly helpful but for people to be effectively saying that the new Bill will stop main contractors going bust and stop any non-payments going down the supply chain is simply untrue.

It would be best if the CIF and other's would advise sub-contractors to simply arrange a contractual link to the client on such projects by way of a collateral agreement. This is the simple solution rather than moaning and groaning about a Bill that may not even work or function correctly. For example, if conciliator here were a plastering subbie for a project for Pespi then the wise thing to do would be to ensure that if the Main Contractor goes belly up I can run to Pepsi to get money due, it is not that difficult to get this agreement in place at the outset.


Links to recent developments as follows;

Irish Examiner

Irish Construction

CIF News Pepsi

CIF News Kilfinane

p.s. Rather than been guilty of random statements myself  I will do another blog separately on the Construction Bill in the near future outlining it's potential flaws. Link below to something I blogged on the topic a few years back.....

Conciliators previous discussion on the Bill

Wednesday, March 9, 2011

CONSTRUCTION CONTRACTS BILL

The new government re-convened today. An item of interest from our industry that will be back on the table for discussion is the proposed Construction Contracts Bill.

The explanatory note on this bill (link attached) is as follows: http://www.oireachtas.ie/viewdoc.asp?fn=/documents/bills28/bills/2010/2110/b2110s.pdf

The main purpose of this Bill is to provide for a mechanism whereby prior notice of an intention to withhold sums from payments otherwise due must be given. Otherwise, payments must be made in full and/or the payee may suspend the provision of works and/or services under the construction contract until payment is made in full. This provision is proposed in ease of persons along the chain in the construction sector who may suffer unduly where an entity under a superior contract would find itself withholding payment unilaterally without cause. This would bear unfairly upon the payee or others dependent upon the payee.

The 'explanatory' note further goes on to say....

Ideally this measure would be linked to wider provision in respect of construction contracts including a more rapid and effective means of dispute settlement. However, that could be considered at a later point in time.

In layman's terms what I believe the Bill is attempting to do and is supposed to be set up to do is to protect the ordinary joe small subbie from the big time bully main contractor.

We already have provisions in the industry for this; these are called Forms of Sub-Contract. Obviously the provisions in these standard sub-contract forms are not deemed strong enough to protect the subbies ? The benefit of having an Act like this is that one cannot contract out of government policy or the law so the terms of the Act form the terms of the Contract which in turn will involve adjudication. Some of the committee stage amendments require further tweaking but all in all I would say this is beneficial for the industry and ensures that smaller subbies are paid fairly and reasonably.

Sub-Contractors would be advised to delete any arbitration clauses from their forms of sub-contract and agree to use adjudication per this new Bill as a form of dispute resolution for all disputes.

I would also have liked to see collateral agreements be made mandatory for sub-contracts over a certain value where the main contract is a state funded project. These contracts are deemed under this Act as not been 'Construction Contracts'

"Construction contracts: exceptions, etc.

2*.—(1) A contract is not a construction contract–

(a) if one or more than one of the parties to the contract is a state contracting entity and the value of the contract is not more than €50,000,


Mandatory collateral agreements for say sub-contracts over 50k in value on state funded projects would help to avoid situations that occurred on the Pierce Construction Schools Projects as the subbies would have a direct contractual link to the funder / state.http://www.rte.ie/news/2011/0304/schools.html

More on this later.........