Tuesday, September 27, 2011

Public Works Contracts - Important Changes

A number of amendments have been made at the end of July 2011 to the PW-CF's.

These include the following:

  • The definition of ‘lands made available’ has changed;
  • A requirement for records included;
  • Changes to Programme Contingency;
  • Disputing an ER’s decision has a finite period;
  • Tighter provisions included in regard to time to submit final statement in order to comply with original intention;
  • Employer liability and insurance provisions revised;
A new clause 1.10 has been added in relation to 'background information'-

"1.10 Background Information

1.10.1 In this sub-clause 1.10 Background Information means any information made available on, before or after the Contract Date to the Contractor or to anyone on the Contractor’s behalf by the Employer or by anyone acting on the Employer’s behalf in connection with the Contractor’s tender for the Contract, which information is not included in this Contract. Background Information also includes any information stated to be ‘Background Information’.

1.10.2 The Contractor acknowledges and agrees as follows:

(1) The Employer has no liability whatsoever to the Contractor in contract, tort, under statute, or on any other basis whatsoever (including negligence and breach of statutory or other duty) in connection with Background Information.

(2) The Employer has not made and does not make any warranty, representation, or undertaking in connection with Background Information.

(3) The Employer has not authorised anyone to make any warranty, representation, or undertaking on the Employer's behalf in connection with Background Information.

(4) Without limiting anything in this sub-clause 1.10, the Contractor irrevocably and forever waives any liability that the Employer may have to the Contractor in connection with Background Information regardless of any of the following circumstances, and the Contractor acknowledges that the Employer makes no warranty, representation, or undertaking in regard to those circumstances:

a) whether or not the Background Information is correct

b) whether or not Background Information is complete

c) whether or not any testing, investigation, surveys, or other work to prepare Background Information was done negligently or in breach of statutory or other duties

d) whether or not those who carried out any testing, investigation, surveys, or other work to prepare Background Information were properly selected or supervised

e) whether or not Background Information was suitable for the purposes for which the Contractor or anyone on the Contractor's behalf might use it

f) whether or not any errors or omissions in Background Information are major or numerous or both

g) whether or not Background Information represents all the information available to the Employer

h) whether or not any works described in Background Information are done as described in Background Information or at all

i) whether or not the Employer had or has other information that might render Background Information misleading

j) the manner in which Background Information was made available

k) whether or not the Contractor had adequate opportunity to carry out any testing, investigations, surveys, or other work or otherwise to verify Background Information.

(5) The Contractor has included in the Contract Sum for the risks that the Contractor has agreed to bear under this sub-clause 1.10"

I'm not fully sure why this new clause is deemed necessary? If the client is bearing no liability for the correctness of the background information then any uncharted or miss-charted services are remediable under the contract in any event.

Another change is that the contract form is attempting to contract out or nullify the contra proferentem rule with the addition of the following sub-clause:

"1.2.4 No rule of legal interpretation applies to the disadvantage of a party on the basis that the party provided the Contract or any of it that a term of the Contract is for the party's benefit."

The doctrine of contra proferentem would possibly come into play in relation to this actual condition itself - this is certainly one for the lawyers and barristers which brings us nicely on to the new Form of Tender and the new Arbitration Act 2010, Section 21.

"We also agree that should a dispute arise under any contract formed by acceptance of this Tender that is referred to Arbitration, to the extent permitted by law, under the Arbitration Act 2010 and a sealed offer has not been made or where a sealed offer has been made and the Contractor's award is greater than the sealed offer, then each party will bear it's own costs in relation to the arbitration proceedings".

Of course it also states in a footnote that if the award is less than or equal to the sealed offer then the Contractor is liable for the costs of both parties.

Unfortunately this is a change to the law by virtue of the Arbitration Act 2010 and it has effectively removed any incentive that the employer had to resolve the dispute before it went to arbitration by making a realistic sealed offer to the Contractor. Now employers can hold off, delay or thwart proceedings on the basis that the worst case scenario for them is a share of the costs, barring extra ordinary circumstances.

The Contract sets out new time provisions on the Employer side which is helpful, prior to this there were no clear or concise time provisions towards the route to dispute resolution. This new clause clearly defines this and encourages the Employers Representative to Act in a Concise Manner:


"10.5.3 If the Employer’s Representative fails to take any of the actions in sub-clause 10.5.1 within the time stated, the Employer’s Representative will be taken to have made a determination under sub-clause 10.5.1(3) that there be no adjustment to the Contract Sum, no use of programme contingency referred to in sub-clause 9.4, and no extension to any Date for Substantial Completion. The determination will be taken to have been made on the last day of the time provided for in sub-clause 10.5.1.

10.5.4 A determination of the Employer’s Representative notified to the Contractor and the Employer under sub-clause 10.5.1(3) or 10.5.2 shall be final and binding on the parties unless, within 28 days after receiving notice of determination (or, if sub-clause 10.5.3 applies, within 28 days after the determination is taken to have been made), the Contractor or the Employer gives notice to the other under sub-clause 13.1.1 disputing the determination and referring the dispute to conciliation.


10.5.5 Notice of an agreement under sub-clause 10.5.1(2) shall be final and binding on the parties unless, within 28 days after receiving the notice, either:
(1) the Contractor both (a) notifies the Employer’s Representative and the Employer that the Contractor disagrees that the notice correctly records agreed terms and (b) gives notice to the Employer under sub-clause 13.1.1 referring the dispute to conciliation or
(2) the Employer both (a) notifies the Employer’s Representative and the Contractor that the Employer does not agree with the terms notified by the Employer's Representative and
(b) gives notice to the Contractor under sub-clause 13.1.1 referring the dispute to conciliation"

The general synopsis on this is the Employer has 20 days to make his determination (like old engineers decision under the IEI form) and this is final and binding unless it is disputed within the 28 day time frame set out.

Finally a most important change is clause 11.5 - final account. This has now become a condition precedent.

If no final statement is given within the time required, the Employer shall be released from all liability to the Contractor under or in connection with the Contract.

All of these changes can be viewed on line and it is remarkable that the Department of Public Expenditure and Reform have only noted these changes as been minor amendments on the news part of the website.